Monday 25 August 2014

New library

With our new library coming along fairly well, on Friday we had two set backs. Firstly there is a potential security / fire issue with the entrance doors. Plus we still have a third of the library that needs to be re-shelved, resulting in there being an additional few days delay on the opening. 

So far a team of myself and two other people have worked 7-8 hour days trying to get the library ready for Thursday. It a shame there is to be a delay. However I feel I would rather open late and completed than half finished and apologising to students. 

On a more positive note I am going to do a write up, for cilip, on my tips for moving. If nothing else I have learnt a lot.  

Image below was taken early Friday morning, this section is now completed, unlike the other side of the library which is Tuesday and Wednesdays task.